Page 169 - Sistema de Riego Laderas Sud
P. 169
ESTUDIO T.E.S.A. CONSTRUCCION SISTEMA DE RIEGO LADERAS SUD
MUNICIPIO DE URIONDO DEPARTAMENTO DE TARIJA
Unitario Total Bs. Unitario Total Bs.
Bs. Bs.
> M01 - OBRAS PRELIMINARES 89.246,99 80.322,29 8.924,70 1%
1 INSTALACION DE FAENAS glb 1 2.496,83 2.496,83 2.247,15 2.247,15 249,68 249,68
2 LETRERO DE OBRA pza 1 680,81 680,81 612,729 612,729 68,081 68,081
3 REPLANTEO TOPOGRAFICO DE RED km 18,32 1.197,44 21.937,10 1.077,70 19.743,39 119,74 2.193,71
4 LIMPIEZA DE TERRENO Y DESHIERVE m² 7.329,40 8,75 64.132,25 7,88 57.719,03 0,88 6.413,23
> M02 - OBRA DE TOMA LADERAS 837.727,03 753.954,33 83.772,70 12%
5 REPLANTEO (ESTRUCTURAS Y EDIFICACIONES) M² 408,73 7,43 3.036,86 6,69 2.733,18 0,74 303,69
6 EXCAVACION CON AGOTAMIENTO M3 604,67 78,59 47.521,02 70,73 42.768,91 7,86 4.752,10
7 EXCAVACION ROCA FRACTURADA C/MAQ Y EXPLOSIVOS M3 21,37 130,52 2.789,21 117,47 2.510,29 13,05 278,92
8 GAVIONES C/DIAFRACMA M3 249 488,28 121.581,72 439,45 109.423,55 48,83 12.158,17
9 GAVIONES COLCHONETA M3 74,7 674,23 50.364,98 606,81 45.328,48 67,42 5.036,50
10 COMPUERTA GUSANO S/DIS PZA 2 287,98 575,96 259,182 518,364 28,798 57,596
11 RELLENO COMPACTADO MANUAL M3 140,54 35 4.918,90 31,50 4.427,01 3,50 491,89
12 HºAº M3 52,59 4.037,19 212.315,82 3.633,47 191.084,24 403,72 21.231,58
13 HºCº CANAL M3 1,33 1.073,88 1.428,26 966,49 1.285,43 107,39 142,83
14 HºCº CAMARAS M3 3,78 1.247,17 4.714,30 1.122,45 4.242,87 124,72 471,43
15 HORMIGON ARMADO PARA TAPAS M3 0,27 3.469,37 936,73 3122,433 843,05691 346,937 93,67299
16 HORMIGON CICLOPEO 50 % P.D. M3 368,06 1.029,60 378.954,58 926,64 341.059,12 102,96 37.895,46
17 PROV. Y COL FILTRO GRAVA CLASIFICADA S/DIS M3 40 172,95 6.918,00 155,66 6.226,20 17,30 691,80
18 PROV/COL. LLAVE FV Ø=3" T.C.+ACCES PZA 1 1.644,28 1.644,28 1.479,85 1.479,85 164,43 164,43
19 REJILLA FE Ø=1/2" S/DIS M2 0,06 440,14 26,41 396,126 23,76756 44,014 2,64084
> M03 - ADUCCION Y DISTRIBUCION 4.533.542,28 4.080.188,04 453.354,23 64%
20 EXCAVACION TERRENO SEMIDURO m³ 4.374,24 61,25 267.922,20 55,13 241.129,98 6,13 26.792,22
21 RELLENO Y COMPACTADO DE TUBERIA m³ 3.274,83 61,25 200.583,34 55,13 180.525,00 6,13 20.058,33
22 CAMA DE TIERRA CERNIDA m³ 727,74 108,98 79.309,11 98,08 71.378,19 10,90 7.930,91
23 PROV. Y TENDIDO TUBERIA PVC D=2" C-9 m 1.507,08 59,76 90.063,10 53,78 81.056,79 5,98 9.006,31
24 PROV. Y TEND. TUBERIA PVC D= 2" C-15 m 117,92 69,36 8.178,93 62,42 7.361,04 6,94 817,89
25 PROV. Y TENDIDO TUBERIA PVC D=2.5" C-9 m 3.315,74 69,58 230.709,19 62,62 207.638,27 6,96 23.070,92
26 PROV. Y TENDIDO TUBERIA PVC D=2.5" C-12 m 976,61 76,72 74.925,52 69,05 67.432,97 7,67 7.492,55
27 PROV. Y TENDIDO TUBERIA PVC D=2.5" C-15 m 295,26 83,85 24.757,55 75,47 22.281,80 8,39 2.475,76
28 PROV.TENDI.TUBERIA PVC 4"C-9 m 3.754,82 127,52 478.814,65 114,77 430.933,18 12,75 47.881,46
29 PROV.TENDI.TUBERIA PVC 4"C-12 m 294,55 142,94 42.102,98 128,65 37.892,68 14,29 4.210,30
30 PROV.TENDI.TUBERIA PVC 6"CLASE 9 m 3.756,67 211,49 794.498,14 190,34 715.048,32 21,15 79.449,81
31 PROV.TENDI.TUBERIA PVC 6"CLASE 12 m 462,25 374,9 173.297,52 337,41 155.967,77 37,49 17.329,75
32 PROV.TENDI.TUBERIA PVC 6"CLASE 15 m 390 440,08 171.631,20 396,07 154.468,08 44,01 17.163,12
33 PROV. Y COLOC. TUBERIA PVC D=8" C-9 m 1.370,00 299,3 410.041,00 269,37 369.036,90 29,93 41.004,10
34 PROV. Y TENDIDO DE TUB FG D=6" m 1.763,87 461,84 814.625,72 415,66 733.163,15 46,18 81.462,57
35 PUENTE COLGANTE 18M(PASO DE TUBERIA 4") pza 1 12.876,99 12.876,99 11.589,29 11.589,29 1.287,70 1.287,70
36 PUENTE COLGANTE 15M(PASO DE TUBERIA 4") pza 2 12.311,43 24.622,86 11.080,29 22.160,57 1.231,14 2.462,29
37 PUENTE COLGANTE 20M (PASO TUBERIA 8") pza 1 17.642,67 17.642,67 15.878,40 15.878,40 1.764,27 1.764,27
SISTEMAS Y PROCESOS DE CONSULTORIA S.R.L.