REHABILITACION DE PALEOCAUCES MUNICIPIO DE VILLAMONTES DEPARTAMENTO DE TARIJA
OFICINA TECNICA NACIONAL DE LOS RIOS PILCOMAYO Y BERMEJO
M07 - INSTALACION SANITARIA 23,116.96
1 EXCAVACION 0-2M SUELO SEMIDURO MANUAL m³ 10.36 61.88 641.08
2 PROV. Y TENDIDO TUBERIA SDR-35 D=2" m 21.45 46.75 1,002.79
3 PROV. Y TENDIDO TUBERIA SDR-35 D=4" m 8.40 87.78 737.35
4 PROV. Y TENDIDO TUBERIA SDR-35 D=6" m 18.10 171.40 3,102.34
5 HORMIGON CICLOPEO ( 1:2:3 - 50% P.D.) m³ 2.39 796.41 1,903.42
6 MORTERO IMPERMEABILIZANTE C/SIKA 4A m² 12.30 31.84 391.63
7 TAPA DE HºAº Fck=250kg/cm2 m³ 0.25 2,987.53 746.88
8 PROV Y COLOC INODORO TANQUE BAJO + ACCES pza 1.00 870.18 870.18
9 PROV Y COL LAVAMANOS PEDESTAL C/REB + GRIF+ ACCES pza 1.00 996.96 996.96
10 PROV Y COL LAVAPLATOS C/REBALSE (2dep+1freg)+ACCES pza 3.00 1,401.92 4,205.76
11 PROV Y COLOC DE DUCHAS + ACCES pza 1.00 722.24 722.24
12 PROV. Y COLOC. REJILLA DE PISO 2" pza 4.00 106.30 425.20
13 PROV Y COLOC CAJA INTERCEPTORA 2" pza 3.00 78.56 235.68
14 PROV Y COLOC DE PAPELERO pza 1.00 63.51 63.51
15 PROV Y COLOC DE JABONERO pza 5.00 53.31 266.55
16 PROV Y COLOC DE TOALLERO pza 5.00 59.67 298.35
17 CAMA DE ARENA E=10CM m³ 1.39 154.78 215.14
18 RELLENO Y COMPACTADO m³ 8.96 42.18 377.93
19 PRUEBA HIDRAULICA m 47.95 0.81 38.84
20 ACCESORIOS INSTALACION SANITARIA gbl 1.00 5,875.13 5,875.13
M08 - INSTALACION ELECTRICA Y AIRE ACONDICIONADO 171,202.09
1 PROV. INST. GENERADOR 3F A DIESEL DE 32KVA 380/220V pza 1.00 65,342.37 65,342.37
2 PROV. INST. TABLERO DE MEDICION TRIFASICO pza 1.00 3,621.26 3,621.26
3 PROV. INST. TABLERO GENERAL pza 1.00 4,032.45 4,032.45
4 PROV. INST. TABLERO DE DISTRIBUCION pza 1.00 2,557.59 2,557.59
5 PROV. INST. TABLERO SECUNDARIO pza 3.00 2,470.71 7,412.13
6 INSTALACIÓN Y PROV. ILUMINACIÓN PUNTO pto 24.00 452.14 10,851.36
7 INST. PROV. TOMACORRIENTES DOBLES C/PUESTA A TIERRA pto 14.00 420.33 5,884.62
8 PROV. Y COLOC. LUMINARIA 1x40W FLUORESCENTE pza 4.00 349.79 1,399.16
9 PROV. Y COLOC. LUMINARIA 14W FLUORESCENTE pza 14.00 87.84 1,229.76
10 PROV. Y COLOC. LUMINARIA EXTERIOR 70W V. S. CON POSTE pza 6.00 1,471.10 8,826.60
11 PROV. E INST. CABLE UNIPOLAR 3x8 AWG SINTENAX ml 65.00 47.91 3,114.15
12 PROV. E INST. CABLE UNIPOLAR 3x10 AWG SINTENAX ml 40.00 39.18 1,567.20
13 PROV. E INST. CABLE UNIPOLAR 2x14 AWG SINTENAX ml 65.00 32.94 2,141.10
14 PROV. Y COLOC. DUCTOS DE PVC DE 1" ml 151.00 13.18 1,990.18
15 PROV. E INST. VENTILADOR DE TECHO pza 6.00 573.51 3,441.06
16 TOMA ELÉCTRICA VENTILADOR DE TECHO pto 6.00 471.81 2,830.86
17 PROV. E INST. CÁMARA DE INSPECCIÓN O.6x0.4x0.6 Mt pza 2.00 853.60 1,707.20
18 PROV. E INST. SISTEMA DE ATERRAMIENTO glb 1.00 2,705.50 2,705.50