                                                                                       OFICINA TECNICA NACIONAL DE LOS RIOS PILCOMAYO Y BERMEJO



                       M07 - INSTALACION AGUA POTABLE                                               4,185.96
                     1  EXCAVACION 0-2M SUELO SEMIDURO MANUAL       m³           2.06     61.88      127.47
                     2  PROV. Y TEN TUB PVC D=1/2" E-40             m           39.60     16.73      662.51
                     3  CLORADOR COMPLETO ENV.PLAST + ACCESORIOS   pza           1.00   1,084.15    1,084.15
                     4  CAMARA DE LLAVES                           pza           1.00    536.98      536.98
                     5  ACCESORIOS AGUA POTABLE                    gbl           1.00   1,530.50    1,530.50
                     6  CAMA DE ARENA E=10CM                        m³           0.92    154.78      142.40
                     7  RELLENO Y COMPACTADO                        m³           1.14     42.18      48.09
                     8  PRUEBA HIDRAULICA                           m           39.60      0.81      32.08
                     9  DESINFECCION DE TUBERIAS (HASTA D=4")       m           39.60      0.55      21.78
                       M08 - INSTALACION SANITARIA                                                 23,116.96
                     1  EXCAVACION 0-2M SUELO SEMIDURO MANUAL       m³          10.36     61.88      641.08
                     2  PROV. Y TENDIDO TUBERIA SDR-35 D=2"         m           21.45     46.75     1,002.79
                     3  PROV. Y TENDIDO TUBERIA SDR-35 D=4"         m            8.40     87.78      737.35
                     4  PROV. Y TENDIDO TUBERIA SDR-35 D=6"         m           18.10    171.40     3,102.34
                     5  HORMIGON CICLOPEO ( 1:2:3 - 50% P.D.)       m³           2.39    796.41     1,903.42
                     6  MORTERO IMPERMEABILIZANTE C/SIKA 4A         m²          12.30     31.84      391.63
                     7  TAPA DE HºAº Fck=250kg/cm2                  m³           0.25   2,987.53     746.88
                     8  PROV Y COLOC INODORO TANQUE BAJO + ACCES   pza           1.00    870.18      870.18
                     9  PROV Y COL LAVAMANOS PEDESTAL C/REB + GRIF+ ACCES  pza   1.00    996.96      996.96
                    10 PROV Y COL LAVAPLATOS C/REBALSE (2dep+1freg)+ACCES  pza   3.00   1,401.92    4,205.76
                    11 PROV Y COLOC DE DUCHAS + ACCES              pza           1.00    722.24      722.24
                    12 PROV. Y COLOC. REJILLA DE PISO 2"           pza           4.00    106.30      425.20
                    13 PROV Y COLOC CAJA  INTERCEPTORA 2"          pza           3.00     78.56      235.68
                    14 PROV Y COLOC DE PAPELERO                    pza           1.00     63.51      63.51
                    15 PROV Y COLOC DE JABONERO                    pza           5.00     53.31      266.55
                    16 PROV Y COLOC DE TOALLERO                    pza           5.00     59.67      298.35
                    17 CAMA DE ARENA E=10CM                         m³           1.39    154.78      215.14
                    18 RELLENO Y COMPACTADO                         m³           8.96     42.18      377.93
                    19 PRUEBA HIDRAULICA                            m           47.95      0.81      38.84
                    20 ACCESORIOS INSTALACION SANITARIA            gbl           1.00   5,875.13    5,875.13
                       M09 - INSTALACION ELECTRICA Y AIRE ACONDICIONADO                           171,202.09
                     1  PROV. INST. GENERADOR 3F A DIESEL DE 32KVA 380/220V  pza  1.00  65,342.37  65,342.37
                     2  PROV. INST. TABLERO DE MEDICION TRIFASICO  pza           1.00   3,621.26    3,621.26
                     3  PROV. INST. TABLERO GENERAL                pza           1.00   4,032.45    4,032.45
                     4  PROV. INST. TABLERO DE DISTRIBUCION        pza           1.00   2,557.59    2,557.59
                     5  PROV. INST. TABLERO SECUNDARIO             pza           3.00   2,470.71    7,412.13
                     6  INSTALACIÓN Y PROV. ILUMINACIÓN PUNTO      pto          24.00    452.14    10,851.36
                     7  INST. PROV. TOMACORRIENTES DOBLES C/PUESTA A TIERRA  pto  14.00  420.33     5,884.62
                     8  PROV. Y COLOC. LUMINARIA 1x40W FLUORESCENTE  pza         4.00    349.79     1,399.16